11.3 Major Schemes

11.3.1 The table below shows the gross and net costs of major schemes to have had money spent, or predicted to spend, in the LTP2 period.  The gross figure includes money received from other sources. The major schemes denoted with an * are those that have been completed and opened, but have had major schemes resources invested in them during the LTP2 period.

Scheme Gross

£k

Net

£k

2006/7

£k

2007/8

£k

2008/9

£k

Manchester/Salford Inner Ring Road* 38078 37896 296 19 714
Urban Traffic Control 15600 15600 0 2000 0
A57 Cadishead Way (Brinell Drive-City Boundary)* 18476 18476 877 497 1593
Glossop Spur 11071 11071 0 0 0
Metrolink Single Contract 307722 204030 2249 6210 0
Northern Orbital QBC* 9255 9255 2258 1775 0
Metrolink Phase 1&2 Enhancement 96043 96043 8187 40109 28100
Metrolink Phase 3a 575011 244300 0 0 68500
Ashton Northern Bypass Stage 2 11900 10400 0 0  
SEMMMS QBC*   23000   23000   4130   3355   2929
Rochdale Interchange 11500 11500 0 0 18000
Leigh-Salford-Manchester guided busway 64900 44700 0 0 4000