11.3.1 Major schemes under construction
|
|
Description |
Total Anticipated Cost |
Cost up to end of March 08 |
Anticipated Completion Date |
Objectives & Outcomes |
|---|---|---|---|---|---|
| Urban Traffic Control | An upgrade, expansion and renewal of the urban traffic control and traffic signal infrastructure. | £10.6m | £2m | 2011/12 | Maintaining and Improve existing transport infrastructure |
| Metrolink 1&2 enhancement | A range of projects to provide essential improvements and renewals to the Metrolink system | £102m
(DfT £58m) |
£48.6m |
22/05/14 |
Alleviation of overcrowding on existing Metrolink by providing additional capacity |
| Metrolink Single Contract | Design and construction of new Metrolink lines | £575m
(DfT £244.3m) |
This scheme's functions were incorporated in Metrolink Phase 3a | ||
| Rochdale Interchange | Construction of a replacement bus station of Rochdale Town Centre | £11.5m | £0.
Work started in financial year 2008-09. |
23/09/10 | Replace unsatisfactory facility |
| Metrolink Phase 3a | Design and construction of 3 new Metrolink lines along with a second depot and additional trams | £575m | £244.3m |
31/08/12 |
To expand the existing Metrolink network, thereby providing a high quality reliable Public transport system |