Major Schemes
Metrolink
The GMITS identifies the expansion of the
Metrolink Phase 1-2 Renewals
A key element of the
- capacity improvements/system reliability works – primarily 8 additional trams together with the associated facilities/upgrades
- Infrastructure works – including
Disability Discrimination Act /personal safety works , track improvements , new ticket vending machines , together with associated project management, design and contingency costs.
A shortlist of four bidders has been drawn up for the supply of trams, and another five companies have been invited to bid to renew the track.The timescale envisaged for the project is:
- Track renewal completed Autumn 2007
- New vehicles in service Autumn 2008
- existing vehicle modifications , stop and equipment improvements delivered under a new concession from January 2007 onwards.
In July 2004 the Secretary of State withdrew funding for the Phase 3 Metrolink extensions owing to the rise in cost of the project. A ministerial working group was set up with DfT to find a way forward and met between September and December 2004. The Government subsequently confirmed that the original offer of £520m was still available for Metrolink expansion in Greater Manchester.
In April 2005, the countywide Integrated Transport Strategy, developed by
Metrolink Phase 3 has now been identified as a priority for regional funding allocation in the regional prioritisation process.
We are now exploring other funding sources, including the

The Metrolink extension to Stockport was submitted in 2001 as a priority major scheme for Greater Manchester. Since then discussions
have concentrated on the funding of the Airport,
Progress on Fully Approved Schemes
This scheme completes the Inner Relief route round the Regional Centre. Construction of the third and final section (Irwell Street/Gore Street) started in January 2004 and all works were completed in November 2004.
This is an essential part of
During the LTP1 UTC major scheme period the following outputs have been achieved:
- Connection of all traffic signal controlled junctions and crossing installations to central computers for either control or monitoring purposes.
- A UTC main system has been installed and commissioned with the capability to operate up to 1200 sites on SCOOT. Currently
1100 sites are connected to this system with 200 operating under SCOOT control and 900 on fixed time plans. Of the sites
currently operating fixed time a further 50 sites are in progress of being modified to allow the operation of SCOOT with the
infrastructure cost of the SCOOT facilities being met through the
QBC top slice, Northern Orbital and SEMMMS programmes. - A new control room has been constructed and commissioned with all control, operation and fault management facilities fully integrated onto a common platform. This local network platform is then connected to a UTMC common data management facility with the facility to communicate to the GPRS network of ‘T’ mobile and to UTMC compliant communications networks.
- The 30 UTC
CCTV cameras in operation in the regional centre are currently being converted onto the BT optical fibre network to give improved picture quality and reduced communicationsrevenue costs. Connections to camera systems inStockport andBury are in progress, these further facilities will allow the UTC control room to monitor 8 cameras roundBury Town Centre and up to 30 cameras around Stockport Town Centre. - The installation of a UTMC compliant communications network is in progress in
Bury Town Centre. This will provide for the connection of some 70 on- street devices in and around the Centre. 28 traffic signal junctions andpedestrian crossing installations will be connected via UTMC OTU’s with 26 sites operating under SCOOT and 2 sites operating fixed time. 9 traffic flow count sites are being installed and an evaluation is in progress of the potential for the provision of a car park guidance and information system. This project shows how it is possible to increase the capacity of the network to provide for the introduction ofIntelligent Transport Systems whilst containing communication costs. UTMC communications provide a cost effective and flexible platform for connectivity of multiple transport control and information devices. - At the commencement of the major scheme project there were over 250 traffic signal controlled junctions with equipment which
was over 20 years old. This number has now been reduced to some 40 sites and of these 15 sites are in progress of being modernised.
This has been achieved through a combination of funding from the UTC major scheme, district schemes, new development projects
and the
QBC programme. Additional benefits have been achieved during the course of this modernisation programme in that the majority of sites modernised have been provided with pedestrian crossing facilities. - A parking guidance and information system comprising 14 car parks and 21 VMS signs is now operational in Stockport town centre
using UTMC compliant GPRS communications and operated from the UTC control room CDMF (common data management facility). The
revenue communication costs of this scheme is less than £12,000p.a. as a result of the use of UTMC compliant equipment compared to the original proposed system which was forecast to have a communications cost of £35,000 p.a.
This scheme has provided a 2.4km bypass of the existing A57 through Cadishead. Construction started in February 2004, and completion and opening to traffic was achieved during 2005, within the budgeted scheme cost of £18.2 million. It has won a national construction award.
Central Park, a major
One Central Park opened its doors to the first intake of students on 3rd October 2005. Designed to be a one-stop shop for training and employment opportunities in new technology, and led by the Manchester College of Arts and Technology (MANCAT), in association with the three Manchester Universities, this state-of -the -art £20M building is an adult learning campus , which caters for up to 900 students.
The £36m Transport Gateway scheme celebrated its opening on 10 November 2005. Funded jointly from the successful LTP bid,
Manchester City Council,
The Oldham
Work is on target to deliver the full package of measures associated with the £9.47M scheme programme of work by March 2007.
Public
Good progress is being made on this £23M scheme, with a number of completed schemes providing benefits for buses and other
road users. Examples of completed schemes include, in Manchester, a £2M safety and
Schemes with Programme Entry or Conditional Approval Status
The following major schemes have been “provisionally accepted” under the previous approval system by DfT and were remitted to the region for advice on priorities in the December 2004 settlement:
Leigh-Salford-Manchester QBC
Following the Public Inquiry into
Both stages of the environmental mitigation measures for the guided section of the busway have been carried out. These included a course of spraying for the eradication of Japanese Knotweed and the creation of new ponds for the Great Crested Newts. The design work for the on-highway, A580 section of the busway, is complete.
The cost of this scheme is still estimated at £42.3m including vehicles. Subject to Full Approval being granted during 2006, we would anticipate the busway becoming operational in 3 - 4 years' time.
A57/A628 Glossop Spur to Mottram-Tintwistle Bypass
The development of this scheme continues to be co-ordinated with the Mottram to Tintwistle Bypass, which is being progressed by the Highways Agency. The schemes have been programmed to enable the statutory procedures to run in parallel such that subject to final approval they can be constructed as a single scheme, through a single contract.
Planning permission for the Spur was obtained in December 2005. The Compulsory Purchase Orders and Side Roads Orders are to be made in the spring of 2006 with a view to holding a Public Inquiry in the autumn of 2006, subject to the receipt of objections.
Tameside MBC anticipates submitting the scheme for ‘full approval’ to the DfT in the summer of 2007. The total scheme cost is now estimated at £8.01m, an increase of £0.901m to take account of inflation.
Ashton-under-Lyne Northern Bypass Stage 2
Planning permission for this scheme was obtained in September 2003. In December 2004, planning permission was also granted for the relocation of the affected Markazi Jamia mosque to a nearby location. Following extensive and complex negotiations, agreement has been reached with the Trustees of the mosque relating to this relocation. Compulsory purchase and side roads orders (CPO and SRO) for the scheme have been prepared. Negotiations continue to purchase land by agreement where possible. Subject to the above, orders could be published in July 2006, with submission to DfT for full approval in October 2007 subject to public inquiry timescales. A start on construction could be made in February 2008. The total scheme cost is estimated at £8.68M, an increase of £0.39M to take account of inflation.
Planning permission was granted in September 2003. This followed delays because of the need to undertake additional ecological surveys to resolve an English Nature objection. During this period, further design work was undertaken to see if the scheme’s cost-effectiveness could be improved, but subsequent traffic modelling proved that other possible solutions were not appropriate. The compulsory purchase and side road orders (CPO and SRO) were made in October 2004. However, following the Government’s decision that the scheme did not represent an immediate priority for funding and would now be referred to the Regions, the CPO and SRO’s were withdrawn. Negotiations continue to purchase land by agreement. It is now anticipated that the scheme will cost £20.8M, because of inflation and changes to the type of structure required at the crossing of the Wigan to Southport railway. The latter results from the change in construction requirement from a jacked concrete box to a more expensive jacked portal bridge, as a result of detailed ground investigations revealing new rock levels.
The scheme has now been identified by the regional prioritisation process as a contingency within the RFA.
JETTS
The £26.3m scheme was included in the 2002/03 APR as a result of the M60
Following the completion of a Scoping Study, consultants were commissioned to undertake Whole Route Implementation Plans for
all of the nine corridors and these were completed in June 2005. A first stage of public
Schemes where Further Information has been Requested
An Annex E was submitted in July 2004 for this scheme and in the December 2004 Settlement letter the response was:
'Ministers have considered the South East Manchester Relief Road major scheme bid and, whilst they accept this scheme is a
recommendation of the South East Manchester Multi-Modal Study and a priority for approval, they are unable to reach a final
decision until the appraisal case has been completed. In particular, there are still some outstanding modelling issues to
be resolved. An initial assessment of the
Carrington – Irlam/Cadishead Link Phase 1
An Annex E was submitted in July 2004 for this scheme and in the December 2004 Settlement letter the response was that the information provided in the major scheme bid was not sufficient for the Department to be able to form a view on the scheme at that time.
Subsequent to the settlement letter,
Major Schemes Bids
As part of the development of the GMITS and the preparation process for Provisional LTP2, work was undertaken to identify
transport problems and opportunities across Greater Manchester on a segment basis, with a particular emphasis in this work
on how transport can help the conurbation achieve its
The scale of the identified investment that is needed reflects the scale of the challenge faced by the transport system in
responding to rapid economic change in Greater Manchester and ensuring that
Public transport can be made attractive for middle and longer-distance trips through investment in segregated systems. Potential
major schemes include low-cost segregated busways, improved public transport interchanges, highway schemes and proposals to
make better use of parts of the
Public transport schemes are balanced by selected highway schemes with an emphasis on providing road access to key
While the Greater Manchester local authorities strongly believe that major investment must form a part of the transport strategy for Greater Manchester, it is acknowledged that the funding for major schemes via the LTP process is limited. We have therefore assessed each scheme against sub-regional and regional objectives as well as value-for-money and deliverability. The results are described in para 5.12.
Policy
In addition to undertaking our own sub-regional assessment, we have also actively participated with the process for producing regional advice on transport priorities for the Regional Funding Allocation.· The following Greater Manchester schemes have been identified as sub-regional priorities and by the region as priorities for LTP Regional Funding Allocation:
- Ashton Northern Bypass Stage 2
-
Bolton Town Centre Public Transport Scheme - Glossop Spur
- Highway
Retaining Walls Strengthening Scheme - Greater Manchester Urban Traffic Control (GMUTC)
- Leigh-
Salford -ManchesterQBC - M60
JETTS QBC - Metrolink Extensions
-
Rochdale Interchange - SEMMMS Relief Road Scheme (RFA contribution to PFI)
- Yellow School Buses
The following Greater Manchester sub-regional priority schemes have been identified as contingency schemes for LTP Regional Funding Allocation:
- Altrincham Interchange
-
Wigan Inner Relief Road
Two sub-regional priority schemes are currently investigating
- A5225 Access
Wigan - SEMMMS Relief Road Scheme
The following schemes were also identified as sub-regional priorities; these will be considered as part of the early package
being developed for the substantive
-
Rail Rolling Stock - Stockport Interchange
In line with
